The Time Line Of The Process  |   ||
Need to do:  |    Date to be done by:  |    Done: Yes or No  |   
Research for the project  |    January 15th 2011  |    Yes  |   
Initial plan for the project (title, aim, etc.)  |    February 10th   2011  |    Yes  |   
Plan for the project  |    March 1st 2011  |    Yes  |   
Location for the project  |    February 20th   2011  |    Yes  |   
Where to get supplies for projects  |    February 20th 2011  |    Yes  |   
How much everything will cost  |    February 24th   2011  |    Yes  |   
How to pay for it (fundraising ideas)  |    February 25th 2011  |    Yes  |   
Building the group blog  |    March 1st   2011  |    Yes  |   
Planning different disaster scenarios   |    February 26th 2011  |    Yes  |   
Planning the fundraiser and publicizing it   |    August 15th   2011  |    No  |   
Executing the fundraiser  |    January 1st 2012  |    No  |   
Earning the whole amount of money  |    February 1st   2012 (first check) April 1st   2012 (final check)  |    No  |   
Picking the construction days and   making travel plans  |    April 10th 2012  |    No  |   
Hiring the workers for the construction days  |    May 20th   2012  |    No  |   
Buying the supplies  |    May 10th 2012  |    No  |   
Transporting the supplies to Bofel  |    June 2nd   2012  |    No  |   
Storing Supplies  |    July 4th 2012  |    No  |   
Construction  |    July 20th   2012  |    No  |   
Opening the water pump  |    July 30th 2012  |    No  |   
Publicizing   the accomplishments on the blog  |    August 10th   2012  |    No  |   
Working to expand the project if   successful and making wells in other parts of senegal  |    Unknown   |    No  |   
Time Line Of Process